Currently Under Construction



Calvert High School - Replacement Project
  • Public School Construction Project
  • Funded by the State of Maryland & Calvert County Commissioners
  • Status: Currently under construction
  • Project Cost: $52,129,000
  • Project Area: 225,000 SF
  • General Contractor - Hess Construction and Engineering Services
  • Architect: Smolen, Emr, Ilkovitch & Associates
  • Project Duration: 42 months
  • Project Scope: Replacement of Calvert High School on the existing school site. Phased construction over 42 months. First Phase occupation scheduled for school year 2012-2013. Second and Third Phase completion scheduled for school year 2014-2015. 
  • Renovation Details (~2MB)